Here is how you can add deadlines to your project

Deadlines are a practical way to present goals in your schedule. Deadlines can be added only in the Gantt charts.

How to add deadlines?

1. Activate the deadline tools by clicking on deadline tool symbol in the top bar .

2. Select + Add new deadline

3. Move your mouse over the schedule and click on the work package and timing you want to add your deadline to.

4. Select if you want to add an internal (yellow) or Contractual (red) dealine by selecting the correct one in the deadline tools in the top bar.

5. Give the deadline a name and save the name by pressing enter on your keyboard.

6. To exit the deadline tools, simply press the Esc key on your keyboard or click the 'X' icon located at the right side of the deadline tools in the top bar.

How to edit existing deadlines?

To edit an existing deadline you have to

1. Activate the deadline tools. 

2. Select the deadline you want to edit by clicking on it.

3.1. To modify the name, simply click on the current name, make your changes, and then press enter to save your edits.

3.2. To delete it, select it and press backspace or delete.

3.3. To move the deadline, drag it to the correct place

3.4. To change the type of deadline, select the deadline you wish to modify and then click on the appropriate type (either Internal or Contractual) located in the top bar.

How do I hide the deadlines?

You are able to hide the deadlines from the eye symbol in the top bar. Open the eye symbol menu and un-select the Deadlines.