Drawings let you see the schedule on a floor plan. You add a drawing to a floor, roof or facade in the space model and trace the outlines of its spaces. Each traced space is then coloured by the status of the work in it, so you can see at a glance which rooms are blocked, late or done.
Before you start
- Setting up drawings needs rights to edit the schedule settings.
- The schedule needs a space model first, because drawings are attached to its spaces. See Building the space model.
- Have the drawing ready as a PDF, PNG or JPG file of up to 40 MB.
Open the drawings page
- Open Schedule settings (the gear next to the schedule name).
- Select Drawings.
The page shows the space model on the left. Each floor, roof and facade has an Add button, and the counters show how many spaces are still left to trace. Spaces still to trace are marked with a dot (To map), and traced spaces with a tick (Mapped).

Add a drawing
- In the space model tree, select Add next to the floor, roof or facade the drawing shows. You can also select the space and then Add drawing.
- Drop the file in the window, or select Choose file.
- Check Covers. It shows the part of the space model the drawing covers. If one sheet shows several floors or areas, select Covers also and click the other parts of the space model to add them.
To try the feature without a file of your own, select Use sample drawing.

To swap a drawing for a newer revision, add the new file to the same part of the space model. Sitedrive tells you which drawing it replaces. Once you have set the new drawing’s scale, Sitedrive asks whether to keep the outlines traced on the previous drawing: select Keep to reuse them, or Not now. Outlines that fall outside the new drawing stay on the list of spaces to trace. To remove a drawing, open it from the tree and select the bin next to the file. Removing a drawing also removes the outlines traced on it.
Trace the spaces
Tracing tells Sitedrive where each space is on the drawing. Sitedrive guides you through the spaces that are still left: the bar above the drawing shows how many remain, with a button for the next one, for example Trace Stairwell.
- Select the Trace button, or pick a space in the tree.
- Draw its outline with one of the tools on the left of the drawing:
- Rectangle: drag a box over the space.
- Polygon: click each corner. Click the first corner, double-click or press Enter to finish. Backspace removes the last corner.
- Select and edit points: adjust an outline you have already drawn.
- Check the space name in the card that opens, then select Next to trace the next space, or Done.

More tools:
- Set scale: click two ends of a distance you know, such as a dimension line, and enter the real distance in millimetres. Sitedrive then shows the measured area of each traced space.
- Crop drawing: cut away empty areas around the plan.
- Show space labels on plan: show or hide the space names on the drawing.
If the drawing shows a space that isn’t in the space model yet, draw it anyway. It gets a name you can change, and Save to space model adds it to the space model with its outline.
See progress on the drawing
In a schedule view, such as Gantt or Takt, select Show drawings (map icon) in the toolbar. The Drawings panel opens beside the schedule.
- Use Previous and Next to switch between drawings.
- Under Panel position, dock the panel to the right or to the bottom, or open it in a separate window. Drag the edge to resize the panel, and double-click the edge to reset its size.
- Move the time cursor to see the situation on another day or week. Select Today to return.
- Select Hide drawings to close the panel.
There is also a Drawing view type that shows progress on a floor plan or facade drawing in its own tab. See Views as tabs.
How spaces are coloured
Each traced space takes the colour of the most urgent status of the work in it, in this order:
Blocked › Delayed (not started) › Delayed (started) › In progress › Open Issues › Ready to start › Planned › Completed › Verified
So a room turns green only when all the work in it is finished. Spaces with no work show “No work”. See Tracking progress for what each status means.
Good to know
- Moving the time cursor changes which work counts as started or late on that date, but reported completion doesn’t move back in time. Work finished yesterday still shows as completed if you move the cursor a month back.
- Only PDF, PNG and JPG files of up to 40 MB are accepted.
- If the browser blocks the separate drawings window, allow pop-ups for Sitedrive and try again.