Team swimlane

The Team swimlane view gives each team its own lane on the timeline. It answers a simple question: what is each team doing, and when? Use it to check a subcontractor’s workload, spot overlaps within one team, or walk through the plan team by team in a site meeting.

Before you start

Creating the view needs the Schedule, Site or Account admin right. Once it is shared, anyone it is shared with can open it as a tab. See Sharing views and locking settings.

Create a Team swimlane view

  1. Click + (View selection and management) in the header.
  2. Click New view → Grouped Gantt ›.
  3. Click Team swimlane.

The view opens in a new tab.

Read the view

  • Each row is one team, for example Electrical or Painting & Flooring.
  • Time runs from left to right.
  • Each bar is a work package in one area, placed on its team’s lane. The area is kept, so you can still see where the team is working.
  • Bars always use the team’s colour.

Good to know

  • Custom colours set with Set color are not shown here; the team colour always wins.
  • Changing a work package’s team moves it to the other team’s lane.
  • Location breakdowns don’t apply to this view.
  • By default, a team’s bars sit on one row so the lane stays compact.